At the turn of July and August, a coordinated inspection of fire safety equipment (EPS - electrical fire alarm system including associated fire protection systems) will be carried out in the buildings of the MU Faculty of Arts according to the following schedule:
- 26 July Building M (Joštova 13)
- 28 July Buildings C, D, E, F
- 9 August Buildings A, B1, B2
As part of the control of fire safety equipment ("PBZ"), a "fire alarm" will be triggered via EPS with subsequent activation and control of downstream fire protection systems (according to the equipment of individual buildings), including activation of the evacuation announcement, which will call for leaving the buildings (it will be clearly audible even in the courtyards). During the test, the operation of lifts will be restricted and the electricity supply to the buildings will be partially disconnected (buildings A, B1, B2, and E).
During the test, the premises will be occupied by MUF maintenance personnel and, to the extent necessary, by companies inspecting downstream fire protection systems (PBZ).