A fire test will verify faculty safety
A practice fire alarm will trigger a test of the fire alarm systems, signalling and evacuation radio in each building.
Noisy work on constructing a new building in the courtyard between Jaselská and Veveří streets will begin on Friday, 15 March. Employees and students of the Faculty of Arts MU, especially those moving around in buildings G and J, must expect increased noise and dust.
Workers will begin piling and building the foundation slab on Thursday, April 4.
The supervising person for the Faculty of Arts MU is Ivo Jurtík - any questions can be directed to him. Inspection day at the construction site is always on Wednesdays.
A practice fire alarm will trigger a test of the fire alarm systems, signalling and evacuation radio in each building.
It follows Faculty of Arts MU Directive No. 2/2022 on methods and principles of internal and external communication. It specifies, for example, the creation of new profiles and also defines content and security rules. It also introduces the Ten rules of social networks.